WJE PROJECTS
Square Lake Road Bridge
CLIENT |
Posen Construction, Inc. |
LOCATION |
Bloomfield Hills, MI |
Water Main Vibration and Settlement Monitoring
The Michigan Department of Transportation (MDOT) funded the demolition and replacement of the East Bound Square Lake Road Bridge over the Grand Trunk Western Railroad. The Detroit Water and Sewer Department (DWSD) operates a 42-inch water main within the right-of-way. DWSD requested that the water main be monitored for potential damage from vibration and settlement related to the bridge demolition and construction.
BACKGROUND
Square Lake Road is one of the main east-west roadways in the northern Detroit suburbs. Adjacent to the I-75 ramp connection, Square Lake Road bridges the Grand Trunk Western Railroad tracks. At this point, the roadway consists of three lanes in each direction.
SOLUTION
WJE developed a monitoring program to ensure that the water main's vibration and settlement during construction did not exceed the limits specified by the DWSD. The vibration monitoring utilized a remotely operated seismograph to minimize the field labor costs, the data from which was downloaded twice a day. Settlement monitoring was also performed by installing telltales and measuring their elevations three times per week with surveying equipment. WJE's monitoring program confirmed that excessive settlement or vibration did not occur during bridge demolition and pile driving operations of the new construction.
RELATED INFORMATION
-
We engage a full suite of state-of-the-art instrumentation and monitoring capabilities to test... MORE >Services | Instrumentation and Monitoring
-
When the integrity or condition of a structure is in question, clients rely on us for answers MORE >Services | Structural Engineering
-
We collaborate with all project stakeholders throughout the design process to ensure the proper... MORE >Services | Systems and Components